CONSTRUCTION UPDATE FROM THE CITY OF WAYZATA:

Below is the proposed schedule for the week of November 1.

Tuesday 11/2: Begin curb installation in newly expanded Vodegel building while beginning to raise manholes along Superior Blvd and Lake Street. The sidewalks along Lake Street will be power washed and installations of trees will also begin.

Wednesday 11/3: Installation of sidewalks on the east side of the Vodegel building while continuing to raise the manhole structures and finish curbs.

Thursday 11/4: The crew will put the final layer of pavement on Lake Street, Superior Blvd and Mill Street while begin paving the newly expanded Vodegel parking lot.

Friday 11/5: Paving will continue and should be completed.

This week, parking on Lake Street will be restricted to allow the contractor to power wash and seal the new sidewalk as well as to allow the final paving of the streets.

Thank you for your patience and cooperation!

Stay tuned to Wayzata.com, your Wayzata Remodeling and Construction leader.