Lake Street Construction Update: Bike Path Paving, Pouring Splash Pad, Restroom Work

Sept. 11 continues to be the target date Stahl Construction estimates that Wayzata’s Lake Street will be completely open.

                         Looking west from the Lake Street Plaza Park, Courtesy City of Wayzata

This week along Lake Street you’ll see Stahl crews working on the following:

  • Continue installing precast benches
  • Prep soil around precast benches for concrete
  • Begin installing the metal panels on the restroom building
  • Pave remainder of the bike path
  • Remove job trailer
  • Begin installing IPE on precast benches
  • Continue landscaping and tree planting
  • Pour concrete for the splash pad
  • Remove and store salvaged items near RR crossings
  • Complete shade structure install
  • Install rock near restroom building

Beyond this week, Stahl projects the following items to be completed by the following dates:

  • Continue installing IPE on precast benches
  • Install finishes on restroom building
  • Pave base course from Barry to Manitoba
  • Pave wear course from Broadway to Barry
  • Painting road striping o Install bike racks
  • Assemble site furnishings
  • Open lake street completely 9/11/2020
  • Plaza area open to the public 9/11/2020 

9/14/2020-9/18/2020

Begin demolition at Barry and Ferndale RR crossings (contingent on receiving permit from BNSF next week)

9/21/2020-9/25/2020

Continue work at Barry and Ferndale RR crossings (contingent on receiving permit from BNSF next week)

———————————-

August 17, 2020

Lake Street Plaza Park Open To Public

The Lake Street Plaza Park, a part of the Lake Street construction project, has been opened to the public.

It is located adjacent to CōV Restaurant.

According to the city of Wayzata, work continues on landscaping and plant installation, sidewalk and concrete pavement construction, irrigation and lighting systems.

READ MORE

——————————-

August 8, 2020

Lake Street Plaza Bathroom Becomes Town Talker

 At the beginning of July, a bathroom facility began to take shape on what was previously the CōV Restaurant parking lot along Lake Street in downtown Wayzata.

It is a portion of a $9 million construction project.

A month later, it has become the town talker.

READ MORE

——————————-

August 2, 2020

Portion Of Lake Street Closed Monday – Wednesday 6a – 5p

According to Stahl Construction, the 600 block of Lake Street in Wayzata will be closed from 6 a.m to 5 p.m. Monday through Wednesday.

The closure will allow the completion of planter bed landscaping.

——————————-

August 1, 2020

Panoway Plaza Work Behind Schedule

As Phase 1 of the Panoway Project moves forward, portions of the work have fallen behind schedule.

The work on the plaza outside of CōV restaurant is one section of that construction.

READ MORE

——————————-

June 21, 2020

$10M For Wayzata Lake Effect Doesn’t Make Special Session Cut

As new asphalt paved the way along Lake Street as part of the Panoway (Lake Effect) Project Phase 1, a $10 million request for Phase 2 stalled at the state Capitol.

A week-long special session ended Saturday morning with many items still on the table.

One of these includes a bonding bill.

But even if legislators passed a bonding bill, both the House version, HF107, and the Senate version, SF4, did not include the $10 million the city of Wayzata had asked for.

This is the second time Wayzata’s request did not make the cut.

READ MORE

—————————————————————————————

March 26, 2020 

Wayzata City Council Moving Forward With Panoway Lake Street Project, Construction Begins Monday

The Wayzata City Council decided to continue moving forward with the Panoway Lake Street construction project at a special emergency workshop meeting on Thursday, March 26.

Construction will begin Monday, March 30.

READ MORE